Industry Report · Framåt In-depth 2026

Top priority, last in line

Why planned maintenance is ranked highest and cut first.

Two-thirds say that planned maintenance is one of their top priorities. Yet, it is cut when budgets tighten, year after year. This in-depth report shows why, what it costs, and what sets the companies that have broken the pattern apart.

314
survey responses
16
interviews
3,692
property plans
Free PDFDirect to your inboxThree decisions to make
The report in numbers

Four figures from the report.

Get the full report
68of 78

have postponed planned maintenance due to the budget situation.

50out of 68

say that the postponement led to more expensive emergency interventions later on.

1,746

SEK/m² in registered maintenance debt among public housing companies in the Planima platform.

85%

of the strategic and data-driven feel well-equipped, compared to 21% of the most reactive.

Insight 1 · From chapter 1
The paradox
The paradox

The contradiction isn't between companies. It's within every organization.

156 out of 237 in Framåt 2026 ranked planned maintenance as one of their top priorities. When the budget was tight, they chose emergency measures anyway, just like everyone else.

Choosing only emergency measures when the budget is tight

Those who rank planned maintenance highest77%
Others78%
Figure 1Framåt 2026 (n = 237), re-analyzed in the In-depth section.
Insight 2 · From chapter 1Insight 3 · From chapter 1
The same meeting, every year
Procrastination is the norm
68of 78

have postponed planned maintenance for budgetary reasons. 59 out of 67 say it recurs, 31 of them every year.

68 out of 78 have postponed planned maintenance for budgetary reasons.

78 respondents, one triangle per person

Have postponed: 68Have not: 10
Figure 2Five new questions for 78 property management professionals, August 2026.
42 of 43

public and municipal housing companies

13 out of 20

private real estate companies

Insight 3 · From Chapter 2Insight 2 · From Chapter 2

None of the ten people interviewed have calculated what the postponement has cost them.

One company delayed pipe replacements for eight to nine years, and in the meantime, paid nearly half the cost of the actual repair on flushing and water damage. Then, the pipe replacement was carried out anyway.

1,746 SEK/m²

Registered maintenance debt in the public housing sector within the Planima platform. What property managers themselves have identified as neglected.

21,800 SEK/m²

Sveriges Allmännytta's estimated renovation needs. A different metric.

The plan is an ambition; the budget is a decision. Maintenance becomes the residual item once all other costs are locked in. No one makes the decision to postpone; it just happens.Christoffer Börjesson, Managing Director of Digital Accelerator, Newsec
In the report

39 pages on why maintenance ends up last.

Two surveys, sixteen interviews, and maintenance plans from 3,692 properties. From the paradox to three decisions that make a difference.

  1. Foreword
    The numbers that didn't add upAnton Lindegren, Head of Professional Services, Planima.
    p. 3
  2. Chapter 1
    The ParadoxDoes the contradiction lie between different property owners, or within each organization?
    p. 5
  3. Chapter 2
    The price of procrastinationWhat does it cost to wait one more year – and why can almost no one answer that?
    p. 12
  4. Chapter 3
    Why is it happening?Four explanations that keep coming back, year after year.
    p. 21
  5. Chapter 4
    What does it take to turn things around?What the companies that made the shift did – and what wasn't enough.
    p. 32
  6. Chapter 5
    Planima's perspectiveOur own stance and an objection to it.
    p. 34
  7. Conclusion
    Change the questionThe question that needs to be replaced and three decisions that make the new one answerable.
    p. 37
From the report · p. 37
Change the question

In every budget dialogue, a question is asked that cannot be answered.

The question being asked today

Do you really need this much money?

The question that can be answered

What did it cost us to wait last year?

01

Write down what didn't get done

Keep what was planned but not executed in the plan for the following year. It is the cheapest change, and it requires no budget increase.

All three decisions, along with how to measure them, are in the report.

Download and read all three
About the data
Framåt In-Depth

Two surveys

314 responses: Framåt 2026 (237) re-analyzed, plus five new questions for 78 people responsible for property management, August 2026.

Sixteen interviews

Ten property owners and six industry representatives and experts.

Maintenance plans

Plans from 3,692 properties at 61 public housing companies in Planima's customer base.

Maintenance debt

1,746 SEK/m² refers to 1,837 properties with registered debt across 57 companies, as of September 2, 2026.

Framåt In-Depth · free PDFDownload